MAJOR ACHIEVEMENTS IN LAST TWO YEARS

A)Work of PFT/Private Sidings completed

PFT

1)PFT of M/s Pristine Mega Logistic Park Pvt Ltd. (PMLPPL) at CHAWAPAILonAmbala Cantt-Ludhiana section commissioned on 28/08/2015.

2)Punjab Logistics Infrastructure Ltd. Multi Modal Logistics Park (MMLP) at Ahmedgarh (PLIL) on Dhuri-Ludihana section commissioned on 03/03/2017.

3)Pvt. Rly Siding for Logistic Park Adani Logistics Ltd at KILARAIPUR (ICD) on Dhuri-Ludihana section commissioned on 30/03/2017. Recently converted to Brown filed PFT on request of the party, Notification issued on 14/09/2017.

4)Central Warehousing corporation having a siding with Warehousing Depot, rail-linked with Nabha station on Rajpura – Bathinda section converted their siding into Brown field PFT, commissioned on 31/03/2017.

Private Sidings

1)Nabha Power Ltd., Thermal power plant of 2100 MW capacity at Sarai Banjara on Ambala Cantt-Ludhiana section, 1st Phase of 1400 MW commissioned on 02/02/16.

B)Sanctioned works completed

1)Doubling AMBALA CANTT-DHAPPAR commissioned on 05/10/2015.

2)Loop lengths at KAULSERI extended on 04/03/2015.

3)Tokenless working bet LEHRA MUHABBAT-BHUCHCHU commissioned on 28/02/2015

4)YAMUNANAGER - JAGADHRI: full rake shunting neck commissioned on 07/07/2015

5)Tokenless working bet BHUCHCHU-BATHINDA CANTT commissioned on 20/12/2015

6)First FOB at BHUCHCHU commissioned on 12/01/2016.

7)IBS between SIRHIND-MANDI GOVINDGARH commissioned on 21/04/2016

8)Panel Interlocking at GNDTP/BATHINDA on 29/04/2016

9)Provision of new freight line at GIDARBAHA : 27/06/2016

10)Extension of running line no. 1, 2 & 3 to hold 43 BCNA/41 BCN at DBN commissioned on 29/11/2016

11)Line no. 3 with Platform at GIDARBAHA converted into running line on 30/03/2017.

12)Extension of freight siding at Ambala Cantt completed on 04/2017.

13)Provision of bituminous flooring of freight siding at Nabha completed on 11/06/2017.

14)Work of Half rake siding at SANGRUR completed on 10/07/2017.

15)Electrification work between UHL-AADR on NLDM-TALWARA section was commissioned on 30.09.2017

C) 

1)First long-haul load run between SAHARANPUR & BATHINDA on 24/06/2016. A total of 163 long haul rakes were run upto Nov’2017.

2)First successful dwarf double stack container trail run from AMBALA CANTT on 02/03/2017.

 

JAN-17 to NOV-17

 

1)TOTAL LOADING - Total loading during March-17 is 713.32 wagons average per day, which is BEST EVERin the history of Ambala Division.

 

2)REVENUE LOADING – Revenue loading during March-17 is 711.26 wagons average per day, which is BEST EVER in the history of Ambala Division.

 

3)TRACTOR LOADING Tractor loading during July-17 is 10.68 wagons average per day, which is BEST EVER in the history of Ambala Division.

4)MISC. LOADING Misc. loading during Sept-17 is 62.07 wagons average per day, which is the BEST EVER in the History of Ambala Division.




Source : Northern Railways / Indian Railways Portal CMS Team Last Reviewed on: 16-01-2018  


  Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.